An uncomfortable silence
At NASA meeting, answers to questions about cost overruns on the Hubble’s successor prove difficult to come by
A+ A- Text Size

At NASA meeting, answers to questions about cost overruns on the Hubble’s successor prove difficult to come by

By Ron Cowen

Web edition: September 17, 2010

Enlarge
Successor to Hubble, the James Webb Space Telescope is now slated for launch in 2014. The $5 billion mission is once again plagued by cost overruns, although no one is saying by how much.
NASA

WASHINGTON, D.C. — How can astronomers advise NASA on how to trim the costs of developing missions if no one will tell them how much the costliest mission of all, the James Webb Space Telescope, is running over budget?

That’s what Alan Boss, chair of the independent NASA Astrophysics Subcommittee, would like to know. When the subcommittee met in Washington, D.C., on September 16 and 17, Boss and his colleagues already knew that the $5 billion infrared space observatory, the Hubble Space Telescope’s successor now set for launch in 2014, was once again in need of a monetary transfusion.

What Boss wanted to know was how much. But no one in room 3H46 at NASA headquarters was willing to talk dollars and sense — when Boss, an astronomer at the Carnegie Institution for Science in Washington, D.C., asked if anyone in the room could cite a dollar figure, his question was met with a silence as deep as any in the vast empty reaches of intergalactic space.

“That’s a lightning rod,” he declared. The subcommittee — and the public — will likely get an answer around October 1, when a study requested in June by Sen. Barbara Mikulski (D-Md.) is expected to be released. But the silence in the room doesn’t bode well for what the report will contain, Boss said during a break in the meeting.

The next day Ed Weiler, associate administrator of NASA's science mission directorate, said he didn't know how much more JWST would end up costing, but likened the problem to a tsunami crashing on the shore.

"Let's put it this way,” he said. “It's going to cost more."

Fear of making a huge and embarrassing error like the one that produced Hubble Space Telescope's infamously misshapen primary mirror may be causing JWST scientists and engineers to go overboard and do too much testing, Weiler said. The comprehensive report on JWST due next month, led by John Casani of NASA's Jet Propulsion Laboratory in Pasadena, Calif., will cite instances where engineers on the mission may be overzealous in testing equipment.

Testing costs were the focus of a report posted online September 16 by the NASA-commissioned Test Assessment Team. The report recommended several ways that JWST, which gobbles up about 40 percent of NASA’s astrophysics science budget, could cut costs. But the Test Assessment Team wasn’t asked to determine the dollar amount that the project, which will image small extrasolar planets and look back in time to see the birth of the first galaxies, has exceeded its estimated cost. Nor was it asked it to document how those overruns came to be.

Potential delays in launching JWST, which costs about a million dollars each day it sits on the ground, as well as added costs to several infrared-sensitive instruments, could threaten funding for NASA’s newest big-ticket space telescopes and other projects recently recommended by the National Research Council in its 10-year plan for astronomy, NASA officials have acknowledged.

Comment
Print Friendly and PDF

Comments (3)

Please alert Science News to any inappropriate posts by clicking the REPORT SPAM link within the post. Comments will be reviewed before posting.

  • The explanation is easy: the Defense contractors are adept at gaming the "system". It's all right in this Country for big corporations to get Welfare, but god forbid an out-of-work familiy get Welfare.

    That there was stoney silence in the room would indicate some in the room knew, but did not dare reveal the Truth, and others were complicit in the Welfare or feared for their jobs.

    Been there, watched it, got the postcard.
    Westtrekker Westtrekker
    Sep. 19, 2010 at 10:44am
  • great article thanks....
    tai rho tai rho
    Sep. 20, 2010 at 1:27pm
  • contractors get costs plus a percentage for profit. The best deal ever. It only takes inflated costs to increase profits.
    northerntropics northerntropics
    Sep. 24, 2010 at 2:13am
Registered readers are invited to post a comment. To encourage fruitful discussion, please keep your comments relevant, brief and courteous. Offensive, irrelevant, nonsensical and commercial posts will not be published. (All links will be removed from comments.)

You must register with Science News to add a comment. To log-in click here. To register as a new user, follow this link.

Follow Us